Oregon Clean Energy Center

Client: Black & Veatch

Location: Oregon, Ohio

Project: Equipment and Piping Installation

Scope: AZCO provided services at the OCE Center where they replaced several aging coal-fired power plants with a 865MW 2 x 1 combined cycle plant to significantly reduce air emissions and increase power output to over 500,000 homes. AZCO installed 60,000 linear feet of balance of plant piping, associated equipment, 3,000 tons of structural steel for the steam turbine building, combustion turbine building, pipe rack, and assisted with start-up.

AZCO’s Fabrication Division provided critical pipe fabrication for the high pressure and low pressure main steam piping, cold reheat steam piping, hot reheat steam piping, and piping for the turbine bypass station as well as all balance of plant pipe spool fabrication.