Merrimack Station Clean Air Project

Client: Public Service Company of New Hampshire

Location: Bow, New Hampshire

Project: Ductwork and Steel Installation

Scope: AZCO's scope of work included the erection of 2200 tons of plate steel and boxed ductwork as well as the insulation and lagging. Also included in the scope for the 475MW plant was 1000 tons of ductwork support steel and miscellaneous steel installation on Units 1 and 2.