Lundin Mine – Humboldt Mill

Client: Gundlach / Lundin Mine

Location: Champion, Michigan

Project: Dust collection and ductwork, piping fabrication, and installation

Scope: AZCO purchased and installed 42,000 feet of carbon steel piping and pipe supports, valves and fittings, and installed 18,000 feet of above ground HDPE piping and equipment including tanks, silos, copper and nickel thickening tanks, pumps, compressors, flotation cells, concentrator building dust collector and ductwork, and the secondary crushing dust collector and dust collection ductwork.

AZCO's Fabrication Division self-performed the procurement and fabrication of all the piping as well as the fabrication of all piping supports and dust collection ductwork.