Azco

Industrial Manufacturing

Subcategory: Foundry / Mills / Metal Casting

Charter Steel – Rolling Division

Client: Charter Steel

Location: Saukville, Wisconsin

Project: Equipment Removal and Installation

Scope: For the finish mill upgrade, AZCO removed the old 4500 kvw motor, modified and grouted the new base plate, rigged, and then installed and aligned a new 7500 kvw motor. AZCO also piped the lube oil system to the motor, along with removing the old electrical drive equipment, and installed all new electrical drive equipment. All work was performed under a very tight schedule and in a confined work space with many other contractors.

AZCO changed out 3 stationary water boxes to new designed traversing water boxes over a 3 year period. We performed the removal of the old and the installation. alignment and piping of the new water boxes.